Supply Explorer
Crude pipeline line

Wasson-Ardmore Crude Pipeline

Sunoco LP (former NuStar Energy assets, acquired 2024)

8 inch, 10 inch, Loop Lines Crude Oil
tariff points on line
0
origins
0
refineries feeding
0
terminals served · 0 named
0
published routes
0

How product moves through this line

Starts at
Wasson Station (Ringgold Pipeline; Enterprise; Plains (listed under Wasson Station))
Delivers along the way to
Ardmore Refinery
Notes
Length 38.48 miles; Capacity 90 MBD; Interconnections: Ringgold Pipeline, Enterprise, Plains; https://www.sunocolp.com/segments/pipelines/view/wasson-ardmore-crude-pipeline

Fed by (1)

Refineries, gathering systems and pipelines that put product into this line.

Facility Type Location Where Basis
Ringgold-Wasson Crude Pipeline Crude pipeline Ringgold, TX Wasson Station confirmed

Hands off to (0)

None on file yet. That is a gap in the research, not evidence there is none.

Delivers to (1)

Terminals and other facilities this line supplies directly: local storage and rack distribution.

Facility Type Location Where Basis
Valero Ardmore Refinery Refinery Ardmore, OK Ardmore Refinery confirmed

If this line goes down

terminals affected
0
no other supply on file
0
1–2 alternatives
0
3+ alternatives
0

Refineries it supplies crude to

  • Valero Ardmore Refinery — loses one crude source

Follows the supply graph: the terminals this line and anything it leaves without input deliver to, and what still reaches each, including other lines of the same carrier at a shared delivery point. Capacity and contracts are not modelled. Agents can run the same check with the MCP tool assess_outage_impact.

Rates

No published rate runs between the tariff points on this line. The carrier files the rates; see its page.

Tariff points

The carrier tariff points that sit on this line (stations it starts from and delivery points along it) with the terminals at each. A breakout or junction several lines share lists the others.
PointTypeLocationProductsTerminals at this pointAlso on

Products & grades

The tariffs on file don’t list grade names for this system.

Tariffs

0 tariffs on file — every rate and point on this page cites one of them.
TariffTypeTitleEffective

Fees & terms

Status & ownership

PHMSA / NPMS
OPID 31454 · NUSTAR LOGISTICS, L.P. · Crude oil · interstate (checked 2025-12-31, PHMSA HL annual report 2025 (OPID 31454; operator of record))
Operator mileage
NUSTAR LOGISTICS, L.P. reports 3,609 onshore miles (2025 annual report): Texas 2,584, New Mexico 543, Colorado 273, Oklahoma 210
By pipe size (in): 6″ 341, 8″ 968, 10″ 1,254, 12″ 599, 14″ 298, 16″ 139, 30″ 11
Operator-wide figures from PHMSA hazardous-liquid annual reports; one OPID can cover several systems.

Rates are pipeline line-haul transcribed from published FERC tariffs; every figure cites its tariff and item. Cost to serve (netback) adds origin spot price and destination fees. "Confirmed" links match a tariff delivery point to the facility; "same city" means the point is in the facility's city — plausible, not proof; "per research" means the facility's research profile names the pipeline as an outlet.